At a glance
  • Ground-mount arrays need foundations and a trench back to the service. Both are excavation and need an 811 ticket.
  • Open yard is often where the septic drainfield and well lines are.
  • Locate before layout, so the array and the trench both miss them.

Where ground mounts go wrong

A ground-mount array wants open, sunny ground with no trees. On a rural or large suburban lot, that description fits the drainfield.

Drainfields need open ground too. Homeowners keep trees and buildings off them. From the surface, a drainfield looks like a nice patch of lawn.

Driving piles or screws through one damages the septic system. The fix costs far more than moving the array would have.

What else is out there

  • The septic tank and the line from the house
  • A well and the water line back to the house
  • Power to the well pump, a barn or a gate
  • Irrigation mains across the field
  • Propane lines from a tank
  • Old farm lines on converted land

Septic and water systems and power to sheds and barns are private lines. An 811 ticket will not mark any of it.

The trench is the longer exposure

The array sits in one spot. The trench back to the main panel crosses the whole yard. On a large lot that can be hundreds of feet, past the well, the tank and every line that feeds the house.

Mark the trench corridor as well as the array footprint.

The National Electrical Code sets 18 inches of cover for PVC conduit and 24 for direct-burial cable. Your trench will reach the depth of most lines it crosses.

Locate before layout

The best order is records, then locate, then design.

  1. Pull the septic permit file from the county health department. It includes a site plan.
  2. Have the tank, the drainfield area and the other private lines located.
  3. Lay out the array and the trench route around what was found.

Carports and commercial arrays

Solar carports go in parking lots. The footings are drilled several feet deep, in a lot full of lighting conduit, storm pipe and irrigation sleeves. Radar reads through pavement, so each footing location can be cleared before drilling.

Questions from solar installers

Do I need an 811 ticket for a ground-mount array?

Yes. Foundations and trenching are excavation under Florida law. The contractor files the ticket at least two full business days ahead.

Can you find the drainfield before we lay out the array?

Often the tank and the lines to it, and sometimes the drainfield itself. The county permit sketch helps where radar cannot confirm the field.

How far from a drainfield does an array need to be?

Ask the county health department. Setbacks come from the septic rules, and they should be confirmed before design.