At a glance
  • Florida law bars demolition until every member utility line in the area is marked and located, or removed.
  • A utility that says it still has live lines in the area stops the job.
  • Utilities handle their own services. Private lines are the owner's to trace and cap.

The demolition rule is stricter

For ordinary digging, Florida lets an excavator proceed with care once the marking time expires. Demolition gets no such allowance.

Section 556.105(6)(b) says an excavator may not demolish in the ticketed area until all member utility lines have been marked and located, or removed. A utility that has not responded stops the job.

The definition is broad too. Demolition covers wrecking, razing, moving or removing a structure. It also covers any earth disturbance that could damage a buried line.

Read every response

A utility can answer the ticket by saying it has active lines inside the demolition area. That answer means stop. Do not demolish until the utility confirms the site is clear.

Check every response on the ticket before the excavator touches the building.

What 811 does not cover

Each utility cuts and caps its own service. That takes care of the power company's drop and the gas company's line to the meter.

It does not take care of what the owner built:

  • Feeds from the main building to sheds, signs and lot lights
  • Water and fire lines past the meter
  • Sewer laterals, grease traps and septic tanks
  • Propane tanks and their lines
  • Wells and irrigation systems
  • Lines that cross the lot to serve a neighbor

That last one causes the worst days. An old shared line can keep the building next door running. Find it before the slab comes up.

How a pre-demolition locate runs

  1. Sweep the footprint and the whole lot, not only the building.
  2. Trace each line to both ends. Mark where it enters and leaves the property.
  3. Flag anything that looks shared or still live.
  4. Hand the field sketch to whoever is doing the disconnects.

After the building is down, the same sketch tells the next contractor where capped stubs were left.

Septic tanks and wells

An old septic tank should not be crushed under a track hoe by surprise. Florida handles tank abandonment through a permit. The county health department holds the septic file for the address. Pull it before demolition starts.

Demolition questions

Can I start demolition when the two-day wait is over?

Not unless every member utility line in the area has been marked and located, or removed. The expired-time allowance that applies to digging does not apply to demolition.

Who disconnects the utilities before demolition?

Each utility handles its own service. Private lines past the meter are the owner's job to trace and cap.

What if a utility says it still has live lines in the building area?

Stop. Do not demolish until that utility confirms the site is clear.